Purpose

This is a staging area for material for which JRA3 is fully or partially responsible in the GN4-2 PLM Processes.

Processes are documented ad interim on Sharepoint pending update of the PLM site.

Any operational material is available at SA2.

The matrix of responsibilities for transition to production is also at SA2

Useful Templates

 

Subtask to Product Mapping

eduGAIN

Target Gate: None. In production.

Main service Documents

NIF:

CBA:

PID:

Roadmap: Proposal for eduGAIN versioning

Service Description: GN3plus PLM Version; GN4-2 SA2 Operations Version.

Service Policy: https://technical.edugain.org/documents - Declaration v2, Consitution v2, other supplemental policies inc. CoCo v1.

Service Design Documents: 

Branding: Materials

e-Science/enhanced eduGAIN support

Target gate: Pilot

Target review date: Feb 13.

Task: 2.

Documents

PID: Draft

CBA: Document., Payback xls

Roadmap: Feature in main eduGAIN roadmap. 

Service Description: Draft

Service Policy: 

Service Design doc: Draft in progress

Pilot plan:

 

Branding/visibility:

SIRTFI

Target gate: Pilot

Task 1.

Documents

CBA: 

Roadmap: Feature in main eduGAIN roadmap. 

Service Description:

Service Policy: 

Service Design doc: 

Pilot plan:

Branding/visibility:

Cross-sector Interoperability

Target gate: Pilot

Task 3

Documents

CBA: 

Roadmap: Feature in main eduGAIN roadmap?

Service Description:

Service Policy: 

Service Design doc: 

Pilot plan:

Branding/visibility:

Simple Service Provider Registration

Target gate: Production

Task 2

Documents

CBA: 

Roadmap: Feature in main eduGAIN roadmap?

Service Description:

Service Policy: 

Service Design doc: 

Operational Requirements:

Operational Docs:

OLA: 

Operational Processes:

User Support:

Branding/visibility:

OIDC eduGAIN Profile

Target gate: Design

Task 3 + task 1

Documents

CBA: 

PID:

Roadmap: Feature in main eduGAIN roadmap, TBD on representing individual roadmap 

High level baseline Service Description:

Service Policy: 

Service Design doc:

Branding/visibility: OIDC Profile of eduGAIN

MFA profile:

Target gate: Design

Target date: Q4 2017

Task 3

Documents

CBA: 

PID:

Service Description: BCP for use of MFA in eduGAIN

Service Policy: 

Service Design doc: 

Roadmap: Product Output is BCP documents. How to represent?

Branding/visibility: 

InAcademia

Target gate: Pilot

Target date: Material ready jan 23.

Task 2

Documents

CBA: (GN4-1 format) - rebaseline to payback schedule during pilot

Roadmap:

Service Description: Section 11 of CBA

Service Policy:

Service Design Documents:

Pilot Plan: Draft

KPIS: Section 5 of CBA

Branding: 

eduTEAMS Basic

Target gate: Pilot

Target date end Feb.

Task 2

Documents

CBA: In Progress,

PID: How does this relate to the GN4-2 workplan?

Roadmap:

Service Description:                          COPaaS.pptx                     (Needs updating/customising)

Service Policy: Source material, needs writing

Service Design Documents:  Market Analysis GN4-1Functional Architecture ; Technical Architecture ; VM Platform

Pilot Plan: TBC - Umbrella in Q1 2017...what else?

Branding: In progress

Baselined Operational Reqs: In prgress

eduTEAMS Advanced

Target gate: Design

Task 2

Documents

CBA: , Market Analysis GN4-1

PID: 

Roadmap:

Service Description: 

Service Policy:

Service Design Documents: 

Branding: In progress

 

IdP as a Service

Target gate: Design

Task 1

Documents

CBA: Draft in progress

Baselined PID:

Baselined Roadmap:

Baselined Service Description:

Baselined Service Policy:

Service Design Documents:

 

Assurance

Target gate: Design

Task 2

Documents

CBA: 

PID:

Service Description: 

Service Policy: 

Service Design doc:

Roadmap: 

Branding/visibility: 

eduKEEP

Target gate: Design

Task 3

Documents

CBA: 

PID:

Service Description: Product Output is BCP documents. How to represent?

Service Policy: Product Output is BCP documents. Policy BCP can be developed, is this what is wanted?

Service Design doc:

Roadmap: Product Output is BCP documents.

Branding/visibility: GÉANT/EC to be acknowledged as sponsor of work. Material to be available on GÉANT website as White Papers/BCP documents.

OIDC Standardisation

Target gate: Design? Pilot?

Task 3

Documents

CBA: 

PID:

Service Description: Product Output is standards, not a service. How to represent?

Roadmap: Product Output is standards, not a service. How to represent?

Service Policy: Product Output is standards, not a service. How to represent?

Service Design doc:

Branding/visibility: GÉANT/EC to be acknowledged as sponsor of work.

 

eduroam

Target gate: None, in production.

Task 4

Main Service Documents:

NIF:

CBA:

PID:

Roadmap:

Service Description:

Service Policy:

Service Design Documents:

eduroam Managed IdP

Target gate: Pilot

Target date: Q2 2017

Task 4

Documents:

PID:

CBA:

Roadmap: roadmap-eaas.pdf - migrate to Shaun's doc.

Service Description: eduroam Managed IdP (external testing)

Service Policy: idem, chapter 2

Service Design Documents:

Pilot Plan:

KPIS (adapted from GN4-1 D9.3):

Branding: eduroam Managed IdP - agreed with KM. Visible only on parts of user interface.