This page contains information about roadmap for devops, but may include description to actual issues and developments.

RESPONSIBLE: Content is defined and maintained by devops team.

 

eduroam devops team is responsible for operating and managing operational side of eduroam. Devops roadmap notes any outstanding activities from the "business as usual". Business as usual implies:

 

ActionDescriptionPriority (1-lowest, 5-highest)StatusDue DateAssigned toComment
eduroam DB ver 2

public draft spec released

 2016.06 (June) eduroam DB ver 2 is revised version of database that
holds information about NROs, IdPs, Service Locations etc
eduroam DB ver 2final spec released 2016.12 (Dec)  

NRO audit

first draft spec released

 2017.01 (Jan) NRO audit is the process of evaluation of the NROs against the
requirements defined in the eduroam policy.
The aim is to gain knowledge of how well NROs are aligned with
eduroam policy and help them to improve the level of the service.
eduroam DB ver 2SW released 2017.01 (Jan)  
NRO auditfinal spec released 2017.03 (Mar)  
eduroam DB ver 2uptake review 2017.05 (May)  
NRO auditfirst audit run 2017.05 (May)  
NRO auditaudit report released  2017.06 (June)  
eduroam DB ver 2close ver 1.0 support 2018.01 (Jan)  
NRO auditspec update released 2018.03 (Mar)  
NRO auditsecond audit run 2018.05 (May)  

 